CMMI认证

Xi’an Future International Information Co., Ltd.-2018-CMMI5

Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: The factor is determined as not affected because all active projects are located in Xi’an.)
Customer: A).Provincial Information Center. B).Provincial Public Security Department.
Size: A).Large. B).Medium. C).Small.
Organizational Structure (Not Relevant: The factor is determined as not affected because all projects are performed by TPD. There is no subsidiary department in TPD.)
Type of Work (Not Relevant: The factor is determined as not affected, because only the software development projects are included in the appraisal.)
Project Types: A).New development B).Upgrading
Sampling Factor Values: Provincial Information Center. (Customer): The projects are committed by ShaanXi Provincial Information Center. The users are the cities government agencies of ShaanXi province. The RD , VAL, PMC and PI works might differ.
Provincial Public Security Department. (Customer): The projects are committed by ShaanXi Provincial Public Security Department. The projects will follow the standard process of organization
Large (larger than 50 person-months) (Size): The projects are categorized as Large size. However, currently, OU has no active Large size project.
Medium(between 20 person-months and 50 person-months) (Size): The projects are categorized as medium size. The processes of PMC, RD, TS, PI and VER might be tailored.
Small(< 20=””> (Size): The projects are categorized as small size. The processes of PMC, QA, RD, TS, PI and VER might be tailored.
New Development (Project Types): The projects develop new software systems.
Upgrading (Project Types): The projects upgrade or develop new modules basing on existed software systems. The processes of RD, TS, PI and VER will differ.
Subgroups: SG 1: The small upgrading projects committed by PIC.
14 People, 3 Basic Units
– Provincial Information Center.
– Small(< 20=””>
– Upgrading
SG 2: The medium development projects committed by PPSD
15 People, 3 Basic Units
– New Development
– Provincial Public Security Department.
– Medium(between 20 person-months and 50 person-months)
SG 3: The medium development projects committed by PIC.
25 People, 5 Basic Units
– Medium(between 20 person-months and 50 person-months)
– Provincial Information Center.
– New Development

版权所有丨如未注明 , 均为原创丨本网站采用BY-NC-SA协议进行授权