CMMI认证

Xiamen Road & Bridge Information Co., Ltd.-2017-CMMI3

Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: Not relevant. Single location in scope)
Customer (Not Relevant: Not relevant. Similar processes are followed for different customers.)
Size (Not Relevant: Not relevant. All projects are medium size projects)
Organizational Structure (Not Relevant: Not relevant. All projects are from the R&D Center)
Type of Work: Relevant. there are two types of work done which impact processes followed. These are: Infrastructure Management System work and Public Services Information sharing platform work
Sampling Factor Values: G1: Infrastructure Management Systems (Type of Work): Infrastructure Management System
G2: Public Services Information sharing Platform (Type of Work): Public Services Information sharing Platform
Subgroups: G1: Infrastructure Management Systems
19 People, 3 Basic Units
– G1: Infrastructure Management Systems
G2: Public Services Information sharing Platform
15 People, 2 Basic Units
– G2: Public Services Information sharing Platform

版权所有丨如未注明 , 均为原创丨本网站采用BY-NC-SA协议进行授权
转载请注明原文链接:Xiamen Road & Bridge Information Co., Ltd.-2017-CMMI3