CMMI认证

Jiangsu Yuanda Information -2015-CMMI3

Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: All development work is conducted in the Jiangsu offices)
Customer (Not Relevant: There are one primary customers Government)
Size (Not Relevant: Projects are classified as Large using the following Size: time<3 months,=”” small;=”” 3months=””>< 6months,=”” medium;=”” time=””> 6 Large)
Organizational Structure (Not Relevant: All work is performed in the R&D Center using the full range of organizational processes)
Type of Work: There is currently 1 New Development project using the full range of organizational processes and 5 Maintenance projects each using appropriate subset of organizational Processes
Sampling Factor Values: New Development (Type of Work): New Development project using the full range of organizational processes
Maintenance (Type of Work): Maintenance of large sized recently developed products using an appropriate subset of organizational processes
Subgroups: Group A: New Development of Large sized project using full range of processes
5 People, 1 Basic Units
– New Development
Group B: Maintenance of Large sized recently developed products using an appropriate subset for maintaining the product
31 People, 5 Basic Units
– Maintenance

版权所有丨如未注明 , 均为原创丨本网站采用BY-NC-SA协议进行授权
转载请注明原文链接:Jiangsu Yuanda Information -2015-CMMI3