| Sampling Factors: |
Location (Not Relevant: All projects are developed in the same city and therefore location does not have an influence on process selection.)
Customer (Not Relevant: Development work is done for the same general customer and therefore this does not influence process selection.)
Size (Not Relevant: All projects are of similar size and this does not influence process selection.)
Organizational Structure (Not Relevant: All software are development by the Development Department and this therefore does not influence process selection.)
Type of Work (Not Relevant: The project development work is similar in nature, following the same life cycle approach, and this does not influence process selection.)
All projects: All projects within the organisational unit. |
| Sampling Factor Values: |
All projects (All projects): All projects in the organisational unit
No projects (All projects): No projects in the organisational unit |
| Subgroups: |
All projects: All projects within the organisational unit.
27 People, 4 Basic Units
– All projects |