| Sampling Factors: |
Location (Not Relevant: All of the Firm”s work is done in Wuxi, China)
Customer (Not Relevant: The Firm develops software using the same process for all its customers. Software quality over cost.)
Size (Not Relevant: The projects are approximately the same size.)
Organizational Structure (Not Relevant: All the projects have the same basic and similar structure with project manager / project lead, team-members etc. Additionally they all share the same OSSP (processes) implementation with no substantial tailoring. Consequently organizational structure does not cause significant variations in the performance of processes.)
Type of Work (Not Relevant: All the Firm”s software development are based on Microsoft development platform with similar technology)
100% Sample: (100% Sample:): All of the OU”s projects are being appraised |
| Sampling Factor Values: |
G1: All of the OU”s projects are being appraised (100% Sample): 100% Sample: All of the OU”s projects are being appraised
G2:Null Set for SAS Input (100% Sample) (100% Sample): (100% Sample): Null Set for SAS Input (100% Sample) |
| Subgroups: |
G1: All of the OU”s projects are being appraised: G1: 100% Sample G1 All Projects Description: All of the OU”s projects are being appraised
17 People, 3 Basic Units
– G1: All of the OU”s projects are being appraised |