| Sampling Factors: |
Location (Not Relevant: No influence on the process implementation because all work is done in Guiyang.)
Customer: Land management,electric transmission line icing,electric transmission line windage.
Size (Not Relevant: No influence on the process implementation, less than or equal to 10 persons.)
Organizational Structure (Not Relevant: No influence on the process implementation because all projects are developed within Geographic Information Center.)
Type of Work (Not Relevant: Only software development) |
| Sampling Factor Values: |
icing (Customer): Monitoring for overhead transmission line icing, daily work report of icing,model computing,GIS demonstration,short message alarm.
windage (Customer): Adjustment for overhead transmission line windage.
lanmtg (Customer): Provides overall solution for highway, including land resources management, collection for industrial distribution,logistics and highway network planning. |
| Subgroups: |
SG1: Data processing, GIS demonstration and statistical analysis for overhead transmission line icing.
12 People, 2 Basic Units
– icing
SG2: Based on different tower-type,adjusting overhead transmission line windage for power grid customer.
20 People, 3 Basic Units
– windage
SG3: Land resources management and navigation for highway.
15 People, 2 Basic Units
– lanmtg |