Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: Location Not Relevant: all basic units” work is conducted in Jinan China, so location will NOT be a factor that will cause differences on how project work is conducted.)
Customer (Not Relevant: Not Relevant: The software development and research center has the same customers who are the Org internal project implementation & installment department and software project department. The same processes are used.)
Size (Not Relevant: Not Relevant: Not Relevant: Size is not important factor that will not have an impact on how product development is performed.)
Organizational Structure: As Org structure is set up based on customers as well as domain applications. The following Development Departments host software development work: Tax software Dept, Army software Dept.
Type of Work (Not Relevant: Not Relevant: there are three types of typical work conducted in the organization: development, service support, and system integration. The planned Org unit includes only development projects.)
Sampling Factor Values: Tax Software Department (Organizational Structure): The department had developed tax soft products to provide software solutions for site implement department.
Army Software Department (Organizational Structure): Army software Dept.
Subgroups: Tax Software Department: The department had developed tax soft products to provide software solutions for site implement department.
73 People, 3 Basic Units
– Tax Software Department
Army Software Department: Army Software Department
43 People, 2 Basic Units
– Army Software Department