AlmavivA-2013-CMMI3

CMMI认证查询 cmmirz 12年前 (2013-04-15) 694次浏览 0个评论
Organization Name:
(组织名称)
AlmavivA
Organizational Unit:
(组织单位)
Divisione IT - Progetti Speciali
Maturity Level:
(成熟度)
Maturity Level 3
Appraisal End Date:
(评估结束日期)
Apr 16, 2013
Lead Appraiser:
(主任评估师)
Giuseppe Satriani
Sponsor:
(发起人)
PIERO ROSSINI , SMERALDO FIORENTINI
Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: 100% of projects within the appraisal scope are executed in Rome. No differences among locations in project execution; the differences could exist based on type of customers)
Customer: Differences exists depending on the type of customer; customers belonging to the “traditional” AlmavivA business use different processes from customers belonging to transportation market sector
Size: Measured by FP. Projects up to 300 FP use a reduced life-cycle (ciclo ridotto); for higher sizes it applies “ciclo completo”
Organizational Structure (Not Relevant: This is the same of Customer variable; the organisational structure reflect the difference among type of customers)
Type of Work: Difference between Development Projects and Maintenance Projects (MEV)
Sampling Factor Values: Operation (Customer): Projects belonging to the “traditional” AlmavivA business (mainly Public Administration)
Transportation (Customer): Projects belonging to customer related to transportation market (mainly railways); the product developped is in any case application software and does not involve embedded one
Ciclo Completo (Size): Projects estimated in more than 300FP
Ciclo Ridotto (Size): Projects with an estimated number of FP less or equal to 300
Development (Type of Work): New applications
Maintenance (Type of Work): Projects to evolve existing applications (in the OU slag are called MEV)
Subgroups: Full DEV Operation: Development projects belonging to Operation areas >300FP
6 People, 3 Basic Units
– Operation
– Ciclo Completo
– Development
Reduced DEV Operation: Development projects belonging to Operation area <>
3 People, 2 Basic Units
– Development
– Ciclo Ridotto
– Operation
Reduced MAI Operation: Maintenance projects belonging to Operation area <>
8 People, 3 Basic Units
– Operation
– Ciclo Ridotto
– Maintenance
Full DEV Transportation: Development projects belonging to Transportation area >300FP
6 People, 2 Basic Units
– Development
– Ciclo Completo
– Transportation
Reduced DEV Transportation: Development projects belonging to Transportation area <>
7 People, 2 Basic Units
– Transportation
– Ciclo Ridotto
– Development