Organization Name:
(组织名称) CenterMine
(组织名称) CenterMine
Organizational Unit:
(组织单位) Development of FMCenter software product
(组织单位) Development of FMCenter software product
Maturity Level:
(成熟度) Maturity Level 2
(成熟度) Maturity Level 2
Appraisal End Date:
(评估结束日期) Aug 07, 2013
(评估结束日期) Aug 07, 2013
Lead Appraiser:
(主任评估师) Youri Metchev
(主任评估师) Youri Metchev
Sponsor:
(发起人) Goran Milanov
(发起人) Goran Milanov
- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: All development of FM Center takes place in the Development center of CenterMine Ltd, in Sofia, Bulgaria)
Customer (Not Relevant: All existing customers receive the same functionality of FMCenter for the duration of their contracts)
Size (Not Relevant: FMCenter is developed within one and the same team located in the Development center of CenterMine Ltd, in Sofia, Bulgaria)
Organizational Structure (Not Relevant: FMCenter is developed within one and the same team located in the Development center of CenterMine Ltd, in Sofia, Bulgaria)
Type of Work: Amount of new functionality (number of story points) developed vs. effort on bug-fixingSampling Factor Values: Major version (Type of Work): Each year new version of FM Center product is developed and received by all existing customers of the product. There is also bug-fixing effort, however the development of new functionality is predominant. All major versions are numbered X.0 where X is 1, 2, 3, etc. Current major version is 5.0
Intermediate version (Type of Work): Intermediate versions are characterized by development of new functionality for a specific customer. This new functionality is received by the existing customers within the next major version. There is also bug-fixing effort, however the development of new functionality is predominant. All intermediate versions are numbered X.Y where Y is 1, 2, 3, etc. Current Intermediate version is 5.1.
Bug fixing/service pack (Type of Work): Bug fixing is a project with small amount of new functionality and predominant effort for fixing bugs found in the current major version. Such projects are started shortly after each major version issue. Bug fixing versions are numbered X.0Y. The current bug fixing version is 5.01.Subgroups: MV: Development of Major version of FM Center product
12 People, 1 Basic Units
– Major version
IV: Development of Intermediate version of FMCenter product
12 People, 3 Basic Units
– Intermediate version
BF: Bug fixing version of FM Center Product
12 People, 1 Basic Units
– Bug fixing/service pack
说明:该信息摘自CMMI官网公示,更多详情请点击这里查看。注:CMMI认证有效期3年,过期链接失效。