(组织名称) Duck Il Industry Co., Ltd
(组织单位) R&D Center
(成熟度) Maturity Level 3
(评估结束日期) Sep 05, 2020
(主任评估师) You Sub Kim
(发起人) Ingu Ji
- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: All works (projects) are performed in one location, so this is not a relevant sampling factor.) Customer (Not Relevant: The way their work is not changed by the customer, so this is not a relevant sampling factor.)
Size (Not Relevant: All works(projects) are approximately small-medium size project (the same size), so this is not a relevant sampling factor.)
Organizational Structure (Not Relevant: Regardless of the organizational structure, a project team is formed from each team. Therefore, it is not a relevant sampling factor)
Type of Work: There are 2 different project types; these are using some different Lifecycle for each other, so type of work is relevant as a sampling factor.
– New Development
– Carry-over Development (the iteration development after first new development)Sampling Factor Values: New Development project (ND) (Type of Work): The projects in this group are new development (or first development of item in iterative development) Carryover Development (CD) (Type of Work): The projects in this group are the iterative development after the first development
Subgroups: ND project Group: The ND project group is new development (or first development of item in iterative development) and follow whole activities in OSSP.
21 People, 2 Basic Units
– New Development project (ND)CD Project Group: The CD project group is the iterative development after the first development and has more tailored processes compared with ND project group.
18 People, 2 Basic Units
– Carryover Development (CD)