(组织名称) Guangzhou Leadcom Information Technology Co., Ltd.
(组织单位) R & D Center
(成熟度) Maturity Level 3
(评估结束日期) Jun 19, 2020
(主任评估师) Bruce Hofman
(发起人) ZhiHong Fang
- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: There is only one location for this organizational unit, so there is no influence on the process implementation from this factor because they all follow the same standard process.) Customer (Not Relevant: All of the customers have no specific requirements that would influence the process implementation, so this factor is not relevant.)
Size (Not Relevant: All projects are of similar size and they follow the standard process so there is no difference in the process implementation based on this factor.)
Organizational Structure: The R&D department is currently composed of two product lines, so this factor does have an influence on the process implementation.
Type of Work (Not Relevant: All projects are software development projects so there is no influence on the process implementation from this factor.)
Sampling Factor Values: File Platform (Organizational Structure): These projects are all development for the file business processing platform. Archive Platform (Organizational Structure): These projects are all development projects for the archive information system platform.
Subgroups: File Processing: These projects are focused on the file processing platform.
10 People, 3 Basic Units
– File PlatformArchive System: These projects are focused on the archive system platform.
5 People, 2 Basic Units
– Archive Platform