(组织名称) Hangzhou Uusense Technology Inc.
(组织单位) R & D Center and Project Management Center
(成熟度) Maturity Level 5
(评估结束日期) Jun 10, 2020
(主任评估师) Hitesh Sanghavi
(发起人) Daqiang Hu
- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: Single location appraisal. It does not impact the way business is done or any process area is enacted. Thus, location is not a potential differentiator.) Customer (Not Relevant: Customers are similar, and there is no differentiation that impacts the way projects are developed. Thus, the customer is not a potential differentiator.)
Size (Not Relevant: Mostly medium size teams. It only affects efforts and duration. All projects follow the same life cycle. Projects follow a single integrated QMS. Thus, size is not a potential differentiator.)
Organizational Structure (Not Relevant: Medium size organization unit. All projects fall under the software development category. Projects follow a single integrated QMS. Thus, this is not a potential differentiator.)
Type of Work: The projects are of 2 types: 1. New product and 2. Enhancements. This impacts processes of Project planning, monitoring, risk management, integrated project management, DAR, metrics and configuration management. Thus, this is a potential sampling factor.
Sampling Factor Values: New Development (Type of Work): These are new projects for the development. Enhancements (Type of Work): These are Enhancements and Maintenance projects for the development
Subgroups: New: These are new projects for the software development
58 People, 3 Basic Units
– New DevelopmentEnhancements: These are Enhancement projects for the manufacturing industry. However the lifecycle followed and PPb/PPMs are applicable to both the subgroups, as the life cycle is similar.
90 People, 5 Basic Units
– Enhancements