(组织名称) Hunan Chain City Digital Technology Co.,Ltd.
(组织单位) R&D Projects
(成熟度) Maturity Level 3
(评估结束日期) Jul 18, 2020
(主任评估师) Jianzhong Liu
(发起人) keting yin
- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: Basic unit location has no effect in the way the activities are performed as they are performed in one single location) Customer (Not Relevant: Each type of customer use the same process to manage the project, so we can consider this factor has no influence in the way the activities are performed.)
Size (Not Relevant: Different size projects use the same process, so this factor is not considered.)
Organizational Structure (Not Relevant: Each project uses the same organizational structure,so we can consider this factor has no influence in the way the activities are performed.)
Type of Work: There are 2 type of projects, one is “Existing system maintenance project”, the other is “New system development project”.
Sampling Factor Values: Existing system maintenance project (Type of Work): This type of project performs function enhancement development on existing systems New system development project (Type of Work): This type of project requires the development of a new software system and requires architectural design
Subgroups: SG1: Existing system maintenance project
26 People, 4 Basic Units
– Existing system maintenance projectSG2: New system development project
18 People, 2 Basic Units
– New system development project