(组织名称) Qingdao Mingzizhixing Technology Co., Ltd
(组织单位) R&D Center
(成熟度) Maturity Level 3
(评估结束日期) Aug 17, 2020
(主任评估师) Alok Goswami
(发起人) Chao Wang
- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: All application and solutions development work is conducted at Qingdao, China. Thus geographical location is not a differentiator for R&D Center at Qingdao Mingzizhixing Technology Co., Ltd and does not make any material difference to the way processes are applied by the OU.) Customer (Not Relevant: All the customers for R&D Center (OU) are external customers belonging to the e-commerce, data and document management domains. Hence the customer type is not a differentiator with regards to process execution.)
Size: There are differences in the way processes are executed depending on whether the basic unit (Project) is Large, Medium or Small size. The sizing construct is as below: 1) Large > 60 Man Months 2) Medium 20 Man Months – 60 Man Months 3) Small < 20="" man="" months.="" the="" difference="" in="" size="" leads="" to="" some="" differences="" in="" processes,="" particularly="" affecting="" rd,="" ts,="" pi,="" ver,="" val,="" pp,="" pmc="" and="" ipm="" process="">
Organizational Structure (Not Relevant: A single management structure governs the OU and there are no multiple structures or any such structural complexities that may result in variations in the way processes are executed by the OU. Thus Organisational Structure is not a differentiator for the OU – R&D Center and does not make any material difference to the way processes are applied to execute work.)
Type of Work (Not Relevant: All basic units perform software application development involving similar requirements that cut across e-commerce, data and document management domains for external customers. The same lifecycle as well as the same QMS processes are used across projects. Hence, the type of work does not make any material difference to the way processes are applied to execute the work in R&D Center (OU).)
Sampling Factor Values: Small Size Projects (Size): These are projects whose size in total Man-Months is less than 20 Man-Months. Medium Size Projects (Size): These are projects whose size in total Man-Months is between 20-60 Man-Months.
Subgroups: Small Size Projects: These are projects whose size in total Man-Months is less than 20 Man-Months.
6 People, 1 Basic Units
– Small Size ProjectsMedium Size Projects: These are projects whose size in total Man-Months is between 20-60 Man-Months.
9 People, 1 Basic Units
– Medium Size Projects