Sunyur Network Technology (Beijing) Company Limited-CMM

CMMI认证查询 cmmirz 4个月前 (10-21) 21次浏览 0个评论
Organization Name:
(组织名称)
Sunyur Network Technology (Beijing) Company Limited
Organizational Unit:
(组织单位)
R&D Center
Maturity Level:
(成熟度)
Maturity Level 3
Appraisal End Date:
(评估结束日期)
Oct 22, 2019
Lead Appraiser:
(主任评估师)
Deepak Manjarekar
Sponsor:
(发起人)
Feng Miao
Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: The scope of appraisal is R&D Center of Sunyur Network Technology (Beijing) Company Limited located at Beijing. No other location is considered. Sunyur Network QMS processes are established at organizational level for Beijing Location. So “LOCATION” factor is not considered for project selection.)
Customer (Not Relevant: R&D Center executes software development projects for procurement intelligent digital solutions for its customers. In all the basic units, standard process defined at organization level with minor tailoring is followed. No significant process change for different customers. So ‘CUSTOMER’ factor is not considered for project selection.)
Size: R&D Center QMS processes does not vary and differentiating for different size of the projects. Projects are categorized as Small projects (Less than 30 Man-months), Medium projects (30 to 50 Man-months) and Big projects (More than 50 Man-months). There is no variation in the work performed in these projects due to project team size and hence all projects are required to follow same processes irrespective of project team size. But “SIZE” factor is considered for project selection.
Organizational Structure (Not Relevant: Organizational Structure is same for all the software development projects executed in R&D Center hence no significant process variation based on organizational structure. So ‘ORGANIZATIONAL STRUCTURE’ factor is not considered for the project selection. Following functions / activities are carried out at organizational Level. 1. EPG 2. QA 3. Testing 4. Training)
Type of Work (Not Relevant: R&D Center executes software development projects using the Waterfall Life Cycle. Same sets of processes are followed for execution of these projects. So ‘TYPE OF WORK’ factor is not considered for project selection.)
Sampling Factor Values: Small Projects (Size): Less than 30 Man-months effort
Medium Projects (Size): 30 to 50 Man-months effort
Subgroups: Small Projects: Less than 30 Man-months effort
14 People, 2 Basic Units
– Small Projects
Medium Projects: 30 to 50 Man-months effort
11 People, 1 Basic Units
– Medium Projects

版权所有丨如未注明 , 均为原创丨本网站采用BY-NC-SA协议进行授权
转载请注明原文链接:Sunyur Network Technology (Beijing) Company Limited-CMM
喜欢 (0)
发表我的评论
取消评论

表情 贴图 加粗 删除线 居中 斜体 签到

Hi,您需要填写昵称和邮箱!

  • 昵称 (必填)
  • 邮箱 (必填)
  • 网址