Adacel (Canada)-2018-Sponsor Requests No ML

CMMI认证查询 cmmirz 2年前 (2018-11-12) 206次浏览 0个评论
Organization Name:
(组织名称)
Adacel (Canada)
Organizational Unit:
(组织单位)
Engineering & Operations
Maturity Level:
(成熟度)
Sponsor Requests No ML
Appraisal End Date:
(评估结束日期)
Nov 13, 2018
Lead Appraiser:
(主任评估师)
Louis Poulin
Sponsor:
(发起人)
Bedros Nalpatian
Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: All management and development activities are conducted at one location. The sample covers 100% of the locations of the Adacel (Canada) organization.)
Customer (Not Relevant: The same processes are used for all air traffic management customers; likewise, the same processes are used for all air traffic control simulation & training customers.)
Size (Not Relevant: Some process components are optional for small projects, but they follow the processes that apply respectively to air traffic management and air traffic control simulation & training solution development.)
Organizational Structure (Not Relevant: Some resources are shared across the organizational unit”s air traffic management or air traffic control simulation & training subgroups, and the same processes are applied within these subgroups.)
Type of Work: Process differences may exist between air traffic management development and air traffic control simulation & training development.
Sampling Factor Values: ATM (Type of Work): Air traffic management real-time software development.
ATC (Type of Work): Air traffic control simulation and training software development.
Subgroups: ATM: Projects dealing with the development of air traffic management systems.
44 People, 9 Basic Units
– ATM
ATC: Projects dealing with the development of air traffic control simulation and training systems.
25 People, 8 Basic Units
– ATC